Change Management Process A September 7, 2005

Posted by Coolguy in Project Management.
Tags:
trackback

Initiation

  • Any person involved in the project effort, can initiate a change request.
  • Change requests are dealt with in accordance with an overall project Guiding Principle of “minimal change”.
  • Change requests generally arise as a result of an issue on the project
    and would be captured in the project Issue Log.
  • Possible reasons might include the discovery of a problem, the need to accommodate changing business processes, or a suggestion for general improvement.
  • The change request is then assigned a unique reference number and change evaluation commences.

Evaluation

  • All change requests must be referred to the Project Management Team and/or the Project Board as appropriate.
  • The Project Manager will assign the Change Request to the appropriate person(s) for evaluation and recommendation for action.

Approval

  • Once the evaluation has been completed and the impact of a change request is understood, the Project Management Team (or Project Board if appropriate) will either approve or reject the change.
Advertisements

Comments»

No comments yet — be the first.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: